University Street Paving Completed Ahead of Schedule

The municipality announced completion of University Street paving two weeks ahead of schedule.

Public Relations Department
Farkha Village Council

The municipality announced today that University Street paving was completed two weeks ahead of schedule, and 8% under the allocated budget.

Project Figures

  • Street length: 2.4 kilometers
  • Actual budget: ILS 230,000
  • Actual duration: 56 days
This achievement reflects efficient planning and a strong commitment to service delivery.

The next phase will include installation of new LED street lighting along the corridor.